Transportation Improvement Program

Year 1 Year 2 Year 3 Year 4 Year 5
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

Steps

  • Financial Element
    • Fiscal Constraint
  • Annual Listing of Projects
  • TPP gives District Statewide Mobility Program (SMP) - allocation
  • Analyze MTP Project List

    Do projects need to be reprioritized?

    • Air Quality Conformity Analysis - if applicable
  • Project Selection Process

    Of projects in MTP.

  • Project Prioritization

    Within funding constraints by category.

  • PPP Process for MTP and TIP
    • Submit Public Notice
    • Hold Public Meetings
  • TAC Review and Input

    Possibly open to public attendance.

  • Draft TIP Created
  • TAC Review and Approval

    Including District.

  • PAC Draft Approval

    Includes public comment opportunity.

  • Submit Final TIP to TxDOT District
  • Financial Statement Creation

    District combines urban and rural TIPs and creates a financial statement.

  • Incorporation of TIPs into STIP

    TPP incorporates rural and urban TIPs into STIP.

  • STIP Statewide Public Hearing

    TxDOT holds statewide public hearing for STIP.

  • STIP Submission to Commission

    TPP submits to Commission for approval.

  • STIP Submission to FHWA

    TxDOT submits STIP to FHWA for approval.

  • FHWA Approves STIP
  • Quarterly Revision Process

    Occurs up to three times.

    • TAC Review and Approval
    • PAC Draft Approval
    • Submit Draft TIP to TxDOT District
    • Receive and Address Comments
    • PAC Final Approval (includes public comment opportunity)
    • Submit Final TIP to TxDOT District
    • Incorporation of TIPs into STIP
    • STIP Statewide Public Hearing
    • STIP Submission to FHWA
    • FHWA Approves STIP